HomeProjects › Richmond

Richmond

The Wilshire Group purchased the Richmond development from the receiver at stage 1 after the development failed midway through the initial land development phase. Maven provided due diligence consultancy then ultimately took over the project from the prior designer and civil engineers.

Due to this development failing early on there were numerous challenges to overcome including outstanding consents (many had not even been applied for), design shortcomings, and missing information. These challenges led to flow on issues that resulted in various rework and even the demolishing of infrastructure that had been incorrectly constructed.

Maven was instrumental in negotiating a new land development contract and getting the civil contractor back onsite and working within just a few weeks of Wilshire purchasing Richmond. All issues were resolved by Maven and practical completion of the civil and infrastructure works were issued just eight months after purchase.

Building platforms were progressively handed over to builders throughout 2016 according to schedule and works were completed within budget and contract value. Stage 1 of 99 homes will be progressively completed and handed over to owners throughout 2017. Stage 2 and 3 design is well underway.

Development Challenges & Special Features
  • 7m high retaining walls
  • 1.4m3/s onsite disposal of stormwater within rock bore chambers
  • 150m of 280mm diameter thrust wastewater lines through basalt and rock boulders
  • Complex overland flow paths within a flat site
  • 10ha of earthworks
  • Progressive handover of platforms to builders within a tight programme
  • Private pocket parks with light and detailed landscaping

Client Reference

“In a nutshell, we chose to work with Maven on the Richmond development because, having worked with several of their team previously, we knew they had the technical knowhow to understand our requirements. We also knew we could trust in them to deliver the best outcomes and that the work would be completed in a timely manner and within budget. Be it council matters, neighbour agreements, contracts, consents and compliance, third-party contractor arrangements or interaction with other consultants, Maven take these challenges in their stride.

Our reasons for choosing Maven have been validated several times over. They undertake civil engineering and land development consultancy work the way that I wish all consultants would. These guys are 100% invested in their profession and in everything they do. They literally live it.”

Mark Peldmanis
GM Development
Wilshire Group

Location

Mt Wellington, Auckland

Size

500+ homes

Client

Wilshire Group

Schedule

Stage 1 handover (99 homes) 2017, design for stages 2 and 3 well underway

"Our reasons for choosing Maven have been validated several times over. They undertake civil engineering and land development consultancy work the way that I wish all consultants would. These guys are 100% invested in their profession and in everything they do. They literally live it." - Mark Peldmanis, GM Development, Wilshire Group

Other Projects